
Explore the evolution of Move
Construction updates 2024
UPDATE #5
2nd October 2024
As the final stages of construction on-site commence, we are excited to see the finishing touches of Move Early Learning Holt taking shape.
Take a look at our latest video content, for a sneak peek into how things are progressing.
We are looking forward to welcoming our first families in November!
This week’s focus includes:
Pouring concrete driveways
Installing internal vinyl flooring
Fitting internal services
Landscaping and fencing
Looking ahead to next week:
Pouring footpaths
Continuing landscaping and fencing
Installing joinery







UPDATE #4
13th August 2024
Our on-site team is full steam ahead, with landscaping work and play equipment installation now underway!
With the scaffold now removed, the façade has been revealed, showcasing our signature Move Orange.
Upcoming work on-site includes:
Internal wall plastering to the upper floor where our Nursery Rooms are located
Installation of our internal finishes including items such as toilets, sinks and hand basins
Move Holt is certainly starting to take shape now!



UPDATE #3
17th July 2024
Our construction team from Pier Projects remains on track to complete construction in October this year.
This week, the team initiated the next phase of work, including external cladding and internal rough-in of services including plumbing and electrical. We are striving to complete the external façade by the end of this month (July), which will enable us to bring down the scaffold and truly bring Move Holt to life!
Recent milestones on-site include completion of the external brickwork & and roof.
UPDATE #2
22nd May 2024
As we transition into the cooler months our builder, Pier Projects, continues to make solid progress remains on track for completion later this year.
The ground floor structure has now been completed and windows have been delivered ready for installation.
We are keen to watch the progress MOVE in the coming weeks!
Recent achievements on-site include:
Completion of the lift shaft structure and retaining walls around the ground floor
Delivery of the upper ground floor frames
Commencement of external stormwater work




UPDATE #1
4th April 2024
Our builder, Pier Projects is excited to announce that Move Early Learning Holt has reached Level 1 structure status.
A major milestone has been the pouring of the Level 1 Post Tension Concrete Slab.
This will allow the rest of the structure to be completed and the centre will start to take shape quickly from here on.
Recent achievements on-site:
Bulk earthwork & excavation
Inground services
Lower ground structure
Achievements coming up on-site:
Driveway and carpark
Ground floor structure including frames & trusses






